Sage 300 CRE does allow the capture of production units. They are captured at the cost code level and can be used to produce a number of productivity KPI's. See additional information below. Hope you find this useful. Some of the Time Capture tools that link to Sage 300 CRE have field capture tools for the production units.
Some of the fields are:
Estimated Production Units
Approved Changes
Total Production Units
Actual Production Units
Production Unit Description
Estimated Labor Hours
Approved Labor Hour Changes
Total Estimated Labor Hours
Approved Labor Hours
Actual Hours
------------------------------
Dennis Stejskal
Director - Construction Strategy
Sage
Beaverton OR