Large Multi-Line Change Orders

  • 1.  Large Multi-Line Change Orders

    Posted 09-02-2025 13:51

    I'm looking for help with large schedule of value changes within SAGE 300 CRE, and any automated options.  To import a large change order on the cost side is easy with import estimates, but does anyone have experience with large multi-line schedule of value changes (Sales/Billing Side)?  I'm not sure you can import or even "write" utilizing a tool like office connector to the Contracts module.  I know I could potentially use Job Central to cut/paste, however my concern there is 1. the system won't tag the transaction as an "approved change", and 2. my experience with Job Central is you still end up going into each individual SOV line within the Contract module to make tweaks within the units portion.  Is there an option I am missing or haven't thought of?  Thanks!



    ------------------------------
    Casey Noyes
    Cost Control Manager
    Sargent Corporation
    Orono ME
    ------------------------------