General Inquiries

Cost package or Sub job

  • 1.  Cost package or Sub job

    Posted 02-18-2020 09:04
    Hello,

    I have SAGE 300 CRE.  I would like to add within a job sub jobs.  For example, Job 21-1111-5000 is for $20M.  Under that job, I want to create 5001 for self performed work for $60K.  Does anyone know how to setup the sub job in SAGE 300 CRE?

    Thanks!

    Julie

    ------------------------------
    Julie Engel CPA
    CFO
    Lueder Construction Company
    Omaha NE
    (402) 339-1000
    ------------------------------


  • 2.  RE: Cost package or Sub job

    Posted 02-19-2020 08:15
    In Sage300, "SubJobs" are called "Extras".  You will find that under Job Cost - Setup - Extras

    https://support.na.sage.com/selfservice/viewdocument.do?noCount=true&externalId=23667&sliceId=1&docLink=true&languageId=&isDocLink=true&currentmsID=MS_Customer&cmd=&openedFromDocument=true&ViewedDocsListHelper=com.kanisa.apps.common.BaseViewedDocsListHelperImpl

    ------------------------------
    Mike Stansbury
    CFO
    NorthPoint Construction Management
    Hudson NH
    (603) 716-6664
    ------------------------------



  • 3.  RE: Cost package or Sub job

    Posted 02-19-2020 09:12

    Julie, if you haven't used them yet, try extras to separately track cost centers within a main job.  If you do not see an extra field during entry, the option may need to be turned on in Job Cost settings


    Sent from my Sprint Samsung Galaxy S9.