  • 1.  Job Progress Billing in Vista

    Posted 01-16-2019 11:24
    Good morning,

    Does anyone know how to roll over the previous month's AIA requisitions in Vista that will include actual amounts billed not % complete of actual costs to current projected costs.  We have over 300 requisitions to create each month and have been doing so manually.  I have to believe that this software has a way to roll the requisitions over from the previous month.

    Thanks for your help on this.  Getting started with monthly requisitions and would love to expedite this process moving forward.

    Lorrie Heller, Assistant Controller
    Manganaro Northeast

    ------------------------------
    Lorrie Heller
    Assistant Controller
    Manganaro Corp.
    Woburn MA
    (781) 838-6745
    ------------------------------


  • 2.  RE: Job Progress Billing in Vista

    Posted 01-17-2019 08:13
    ​Have you set your Options to "Item Unit Entry" in JB Progress Billing so you can enter units rather than % complete? Also, since a typical AIA does not show quantities we customized the JB Progress Invoice By Bill Group to print landscape and show units billed as well as dollars.

    ------------------------------
    Paul West
    Director of Enterprise Applications
    The Middlesex Companies
    Orlando FL
    (407) 206-0077
    ------------------------------



  • 3.  RE: Job Progress Billing in Vista

    Posted 01-17-2019 09:28
    Hi Lorrie -

    Just to clarify, are you saying Bill Number #1 amounts are NOT rolling to Bill Number #2 (as an example) as previous billed?​

    What are your selections in JB Company Parameters? Do you have 'Allow Changes to Previous and Contract amounts unchecked and Automatic update of PrevBilled and Chg Order amounts on future bills checked?
    ​​​​

    ------------------------------
    Sarah Stegman
    Director - Construction Software Consulting
    CohnReznick LLP

    (469) 371-7209
    ------------------------------



  • 4.  RE: Job Progress Billing in Vista

    Posted 01-17-2019 12:19
    This is an excellent conversation.  Wondering if this data is available through any of HQ surveys or benchmark data?

    ------------------------------
    Kathy Cole
    President
    DK Cole Company, Executive Search
    Downers Grove IL
    (630) 971-2990
    ------------------------------



  • 5.  RE: Job Progress Billing in Vista

    Posted 01-17-2019 14:22

    Thank you for all of your help and suggestions.  The problem I had was with my test data base not being updated in real time and not the VP software application.  The JB Bill Initialization function does in fact pull the previous amounts billed into the current month's progress bill (AIA).  You still have to enter some information manually:

     

    Previous Cert for Payment

    Previous Retainage

    Amount Paid to date

     

    This function does expedite the requisition process tremendously.  I almost feel silly that I did not know about this capability before.  As a relatively new user to Vista, I had relied upon what I was told the system could or could not do.  I am always trying to find new ways to improve the workflow process utilizing our software and thank everyone who jumped in to assist, including Viewpoint customer support who promptly contacted me today. 

     

    Lorrie Heller 

    Assistant Controller

    <a href=image002.jpg@01D20E96.4C3B8CA0">

    Drywall  |  Firestopping |  Specialties 

                 Doors Frames Hardware

     

     

    52 Cummings Park

    Woburn, MA 01801

    Office Direct   781-838-6745

    Office Fax        781-937-8882

    Mobile              781-382-8157
    Website            www.manganaro.com 

     

    STATEMENT OF CONFIDENTIALITY: The information in this message is privileged and confidential and is intended only for the use of the individual or entity named above. If the reader of this message is not the intended recipient, you are hereby notified that you are prohibited from disseminating, distributing, or copying the information contained in this message.

     

     


    ______________________________________________________________________
    This email has been scanned by the Symantec Email Security.cloud service.
    For more information please visit http://www.symanteccloud.com
    ______________________________________________________________________





  • 6.  RE: Job Progress Billing in Vista

    Posted 01-18-2019 12:43

    I believe you will find the you won't need to enter the Previous Cert for Payment, Previous Retainage, and Amount Paid to Date manually once you have rolled the previous billing to the current month.  They will pre-fill along with the information on the schedule of values. 

     

    Dianne Jackson
    CFO

    CMSWillowbrook
    3108 S. 9th St.
    Chickasha, OK  73018
    405.224.1554 tel
    405.590.2641mobile
    405.224.5995 fax


    dianne.jackson@cmswillowbrook.com

     

    www.cmswillowbrook.com

     



     



    This email and any files transmitted with it are confidential and intended solely for the individual or entity to which they are addressed. This email in no way, without a signed attached copy of a contract, constitutes a binding contract.